Data Centre Intelligence Hub

Data Centre Power Infrastructure in Australia

Power is now the main constraint on Australian data centre development. AEMO's 2026 Electricity Statement of Opportunities forecasts that data centre electricity use in the National Electricity Market will grow from about 5 TWh in 2025-26 to about 34 TWh in 2035-36, or from roughly 3% to 13% of grid-supplied electricity. Network businesses reported 225 data centre projects seeking a combined 67 GW of connection capacity, up from 38 GW a year earlier.

In 2026, federal, state and network policy all moved towards one principle: data centres should pay for the grid infrastructure they need and should support new generation rather than drawing on existing supply.


Why Power Is Central to Data Centre Development

A data centre is an electrical facility that also houses computers. Its capacity is described in megawatts because power, not floor space, limits what it can host. Three things follow:

  1. Site selection follows grid capacity. Industrial land is widely available. A connection of several hundred megawatts on a known date is not. Transgrid says Sydney basin capacity "may soon be fully utilised by new connections".
  2. Project timing follows connection timing. A building can be finished before its full grid connection is available, so developers phase their capacity to match the connection.
  3. Operating cost follows energy price. Electricity is the largest operating cost for most data centres, which is why operators sign long-term power purchase agreements.

Grid Connections

Large data centres connect at transmission level (in NSW, usually 132 kV or 330 kV) or at high-voltage distribution level. They normally have an on-site substation.

State or territoryTransmissionDistribution (main metro)Market
NSW and ACTTransgridAusgrid, Endeavour Energy, Essential Energy; Evoenergy (ACT)NEM
VictoriaAusNet (main transmission owner)CitiPower, Powercor, Jemena, United Energy, AusNetNEM
QueenslandPowerlinkEnergex, Ergon EnergyNEM
Western Australia (SWIS)Western PowerWestern PowerWEM (separate from the NEM)

How capacity is allocated in NSW

Since 14 August 2026, Transgrid's Network Capacity Allocation Policy applies to loads of 30 MW or more:

  • Capacity is allocated only when a network connection agreement is signed.
  • Conditional agreements require evidence of progress on permits, land ownership, construction, equipment procurement and financing.
  • Conditional capacity lapses if planning criteria are not met within three months.

Substations & Transmission

Transgrid reports more than 10 GW of data centre connection enquiries within 12 km of its Sydney West substation since late 2024, and more than 20 GW across NSW. w.media reports that about 1.5 GW of Greater Sydney capacity is already in signed connection agreements. A proposed South Creek substation could add about 2 GW more in Western Sydney.

Transgrid has said that new Sydney transmission capacity will be funded by data centres. NSW legislation introduced on 5 August 2026 (the Electricity Infrastructure Investment Amendment Bill 2026) would extend renewable energy zone access scheme powers to large loads of 5 MW or more, so that data centres bear the cost of the network infrastructure their load requires (Energy-Storage.news).


Data Centre Power Demand

How much electricity do Australian data centres use?

About 5 TWh a year in the NEM in 2025-26, roughly 3% of grid-supplied electricity, according to AEMO's 2026 ESOO. AEMO's 2025 ESOO had estimated about 4 TWh (2.2%) for FY2025.

MeasureFigureSource
NEM data centre consumption, 2025-26~5 TWh (~3%)AEMO 2026 ESOO
Forecast, 2035-36~34 TWh (~13%)AEMO 2026 ESOO
NSW share of NEM data centre consumption66%AEMO 2026 ESOO
Victoria's share30%AEMO 2026 ESOO
Projects in connection processes225, 67 GWAEMO 2026 ESOO (network service provider data)
Projects on 2025 list since cancelled~36%, including more than 30% of those classed as committedAEMO 2026 ESOO
Data centres' share of NSW peak demand~3% now; ~20% by 2035Transgrid, via w.media

The gap between 67 GW of connection requests and a forecast of 34 TWh of annual use (about 3.9 GW average load) shows how speculative much of the pipeline is. Many projects lodge enquiries in more than one location, and many will not proceed.


Renewable Energy

Operators are contracting renewable generation to cover their consumption and to meet customer and government expectations:

  • Amazon signed nine PPAs in April 2026 totalling 430 MW in NSW and Victoria. Eight include co-located batteries, and they are its first solar-plus-storage PPAs outside the US (Energy-Storage.news).
  • Firmus says Project Southgate aims to support up to 5.1 GW of new renewable generation (Firmus).
  • Project Meridien (Kimberley) proposes its own wind, solar, battery and gas supply.

The federal Expectations of data centres and AI infrastructure developers (23 March 2026) ask operators to support the energy transition without increasing prices for other users. They are not legally binding.


Power Purchase Agreements

A PPA is a long-term contract to buy electricity, or the renewable attributes of electricity, from a generator. Data centre PPAs in Australia are usually:

  • Physical or retail-backed. Energy flows via a retailer to the site.
  • Virtual (financial). A contract for difference against the spot price, with renewable certificates transferred.

The Australian Energy Market Commission's August 2026 recommendations would use the REGO renewable certificate scheme and require firming contracts for large data centres (see Power Constraints, below). Once adopted, those rules would affect how PPAs are structured and accounted for.

More: Data centre energy suppliers


Backup Power

Every large data centre has backup power to keep running through grid outages:

  • UPS systems bridge the seconds between an outage and generator start.
  • Diesel generators carry the load for longer outages. Fleets are large: NEXTDC S7 proposes 340 generators, and the Mamre Road campus between 842 and 852.
  • Fuel storage is sized for a set runtime, often with refuelling contracts.

Generators are the most contested element in planning, because of testing emissions and noise. Alternative fuels (such as renewable diesel) and batteries are being looked at to reduce generator runtime.

More: Generators · UPS


BESS

Battery energy storage systems (BESS) are taking on several roles at data centres:

  • Load smoothing between the data centre and the grid
  • Speed to power: storage can reduce the firm grid capacity a site needs, which can help with connection timing
  • Backup alongside, or partly replacing, diesel generators
  • Firming renewable PPAs, as in eight of Amazon's nine April 2026 PPAs

Quinbrook's Supernode in northern Brisbane shows the model at grid scale. Stage 1 (260 MW / 619 MWh) began commercial operation in February 2026, on a site originally announced as a data centre campus.

More: Data centre battery storage


Power Constraints

2026 policy changes affecting data centre power:

DateBodyChange
23 Mar 2026Australian GovernmentExpectations of data centres and AI infrastructure developers (non-binding)
28 Jul 2026 (published 5 Aug)AEMCFour recommendations to energy ministers: renewable certificates via REGO, firming capacity contracts, market registration for large data centres, support for co-located generation and storage
5 Aug 2026NSW GovernmentElectricity Infrastructure Investment Amendment Bill 2026 introduced
14 Aug 2026TransgridNetwork Capacity Allocation Policy takes effect
17 Aug 2026NSW GovernmentNSW Data Centre Policy Framework: no net cost to consumers; data centres fund additional energy and water supply
Aug 2026National CabinetConsidered a national framework; federal legislation expected early 2027
22 Sep 2026Victorian GovernmentSustainable Data Centre Action Plan: new data centres to bring their own renewable supply and storage (Premier of Victoria)

Sources: Energy-Storage.news, NSW Government.


Major Australian Projects

ProjectPower-related details (public)
NEXTDC S7On-site substation; 340 backup diesel generators
Mamre Road campus1 to 1.2 GW; 842 to 852 generators; 14,430 kL of diesel storage in the original application
Western Downs Digital Park2.16 GW peak; direct connection to a major substation, bypassing the Ergon distribution network
Goodman SYD0190 MW of secured utility power for 61 MW IT
Project MeridienOff-grid: wind, solar, batteries and gas

Power Infrastructure Suppliers

Electrical contractors · Generators · UPS · BESS · Energy · Engineering


Frequently Asked Questions

How much power does a data centre use in Australia?

Individual facilities range from a few MW (edge and enterprise sites) to hundreds of MW (hyperscale campuses). The largest current proposals are measured in gigawatts: Western Downs Digital Park at 2.16 GW peak and the Mamre Road campus at 1 to 1.2 GW.

Will data centres increase electricity prices?

Governments are writing rules to prevent it. Transgrid, the NSW framework and the AEMC recommendations all aim to make data centres pay for the network upgrades and new supply they need. Whether that works will depend on implementation.

Where can new data centres get grid power?

Sydney basin transmission capacity is largely committed. Transgrid has pointed to regional NSW areas such as the Hunter and Riverina as possible alternatives, and current proposals also target regional Queensland, Tasmania and the Kimberley. Each option trades grid availability against distance, workforce and connectivity.


Supplying Data Centre Power Infrastructure?

Power is now the first decision on every data centre project, so electrical, energy and storage suppliers are engaged earlier than ever. AISB helps power infrastructure suppliers reach developers while projects are still being scoped.


Sources & Verification

  • AEMO 2026 ESOO, 25 Aug 2026, via w.media. Link
  • Transgrid: Data centres and electricity capacity in NSW. Link
  • w.media: Transgrid Sydney capacity. Link
  • Energy-Storage.news: Policy on three fronts. Link. Amazon PPAs. Link
  • NSW Government: Data Centre Policy Framework. Link
  • Quinbrook: Supernode Stage 1. Link

See something that needs updating? Submit a correction.

Trusted by ambitious businesses
Coolaroo client logo
MSP client logo
NSK client logo
ECI client logo
Just Junk client logo
Equalexes client logo
Property With Superannuation client logo
A Plus Cosmetic Clinic client logo
Baran de Bordeaux client logo
Joint's Up client logo
Pacific Fuel Solutions client logo
Shafer Design Limited client logo
Dr M Janjic client logo
Elisha Engineering client logo
Extreme Global client logo
GF Flow System client logo
Humphries client logo
Frontier Pools client logo
Katarzyna Mackenzie Plastic Surgeon client logo
Yeomans Survey Solutions client logo
Marina Specialists client logo
The Oral Care Company client logo
Operation Restore Hope client logo
Patara Life client logo
Dr Tristan de Chalain client logo
Mo Cullen Shirtsmith client logo