Supplier category

Generators for Australian Data Centres

Backup generators keep a data centre running when the grid fails. On Australian hyperscale campuses they are installed in very large numbers: 340 in NEXTDC's S7 application at Eastern Creek, and between 842 and 852 in the Mamre Road campus application at Kemps Creek. They are also the part of a data centre that draws the most planning scrutiny, because of emissions, noise and fuel storage.


The Role of Generators in Data Centres

When grid power is lost, UPS systems carry the IT load for seconds to minutes. Generators start, synchronise and take over the load for as long as the outage lasts. The generator package covers:

  • Generator sets: engines, alternators, controls and enclosures
  • Paralleling switchgear: synchronising multiple units onto a common bus
  • Fuel systems: bulk storage tanks, day tanks, transfer pumps and polishing
  • Exhaust and acoustic treatment: stacks, silencers and acoustic enclosures to meet noise conditions
  • Emissions controls: where required by consent or EPA licence conditions
  • Controls integration with the electrical and building management systems

Key Infrastructure Requirements

Redundancy

Generator fleets are sized so the facility can carry full critical load with one or more units unavailable (N+1 or higher), often per data hall or block.

Fuel storage

Storage is sized for a defined runtime, with refuelling arrangements for longer outages. Volumes are large: the original Mamre Road campus application listed 14,430 kL of diesel storage, and an amended version reported by Urban Digest listed 15,842 kL. Storage design brings in dangerous goods, bunding and fire safety requirements.

Alternative fuels

Operators are looking at renewable diesel (HVO), which can often run in existing diesel engines, and at reducing generator runtime by using batteries. The federal Expectations and state frameworks on emissions add pressure to reduce diesel use.

Load testing

Generators are tested regularly under load, often against load banks, to prove they will start and carry load. Testing schedules are a common planning condition. Catholic Schools Parramatta Diocese asked for Mamre Road campus generator testing to happen outside school hours and peak outdoor activity periods.

Maintenance

Planned maintenance, fuel quality management, battery and starter checks, and periodic full-load tests.

Commissioning

Factory witness tests, site acceptance tests, then integrated systems testing that simulates utility failure across the whole electrical system.


Australian Generator Suppliers

Directory listings for this category are being verified before they are published. Supply to data centre projects? Add your company to be considered.

TypeTypical scope
Generator OEMs and distributorsSupply, factory testing, warranty
Installation and integration contractorsPlacement, paralleling, exhaust, acoustic
Fuel system specialistsTanks, pumps, polishing, refuelling contracts
Load bank providersCommissioning and periodic testing
Maintenance providersService contracts with guaranteed response times

Selecting a Supplier

  • Production slots and lead times. Large generator orders need early commitment. Ask about delivery windows and the supplier's order book.
  • Emissions and acoustic compliance with the consent conditions and EPA licence, including testing regimes.
  • Paralleling experience at the scale of the campus.
  • Service network: technicians and parts near the site, and refuelling logistics.
  • Fuel flexibility: compatibility with renewable diesel.

Current Project Demand

ProjectGenerators (public documents)Stage
Mamre Road campus842–852 (by document version)Amended SSD
NEXTDC S7340Prepare EIS
STACK SYD01188 (as reported at SEARs)More information required
CDC KC1Backup diesel generators (number not stated)SEARs

Planning submissions on Western Sydney projects repeatedly raise generator testing, air quality and diesel storage. Objections to Goodman's Project Atlas include technical concerns about generator testing thresholds and environmental protection licensing. Suppliers who can show low-emission options, acoustic performance and well-managed testing regimes answer the questions planners are asking.


Relevant Data Centre Projects

Western Sydney projects · All projects · Data centre power


List Your Company


Grow Your Data Centre Pipeline

Generator orders are placed early, often before a head contractor is appointed. AISB helps generator suppliers identify projects at the planning stage and reach the developers and engineers who specify backup power.


See something that needs updating? Submit a correction.

Trusted by ambitious businesses
Coolaroo client logo
MSP client logo
NSK client logo
ECI client logo
Just Junk client logo
Equalexes client logo
Property With Superannuation client logo
A Plus Cosmetic Clinic client logo
Baran de Bordeaux client logo
Joint's Up client logo
Pacific Fuel Solutions client logo
Shafer Design Limited client logo
Dr M Janjic client logo
Elisha Engineering client logo
Extreme Global client logo
GF Flow System client logo
Humphries client logo
Frontier Pools client logo
Katarzyna Mackenzie Plastic Surgeon client logo
Yeomans Survey Solutions client logo
Marina Specialists client logo
The Oral Care Company client logo
Operation Restore Hope client logo
Patara Life client logo
Dr Tristan de Chalain client logo
Mo Cullen Shirtsmith client logo